32,490 Trees for 3,000 MW: Is Maharashtra Cutting a Forest to Save the Planet?
A Class-I forest in Karjat is being cleared for India's largest pumped-storage power plant. Actor Sayaji Shinde, villagers and green groups say the Sahyadri cannot be replanted; the government and Torrent Power say clean energy needs storage. Here is the full picture, in numbers.

It is the most uncomfortable question of India's clean-energy decade: can you cut a forest in the name of green power?
In Karjat taluka of Raigad district, that question now has a number attached to it — 32,490 trees. That is how many trees the Maharashtra Forest Department cleared for felling on 14 October 2026 for the Saidongar-I pumped-storage project being built by a Torrent Power subsidiary. The Union Environment Ministry had granted environmental clearance on 12 January 2026.
The project at a glance
| What | Details |
|---|---|
| Project | Saidongar-I Karjat open-loop pumped storage |
| Capacity | 3,000 MW — India's largest pumped-storage plant when ready |
| Estimated cost | ₹13,505 crore |
| Land | 377 hectares, of which 233 hectares is forest |
| Villages named | Bhaliwadi, Ambod, Potal, Pali, Saidongar, Dhak |
| Trees approved for felling | 32,490 |
| Replanting promised | 90,000 saplings (30,000 on site, 60,000 in Satara) |
Why people are angry
Residents and activists point out that this is a Class-I forest that is home to leopards, sloth bears, wolves, sambar, four-horned antelope and Indian pangolins, along with raptors such as ospreys and black eagles. Karjat lawyer and activist Kailash More, who leads the local protest, warns that the damage cannot be undone and that heavy tunnelling in a landslide- and earthquake-prone hill belt adds risk.
On 7 November, at a gathering in Karjat, actor and tree-planter Sayaji Shinde turned the issue into a question about land and middlemen. He recalled that his own family land went under a dam in 1978 for a compensation of about ₹14,000, and that it took nearly 40 years and endless paperwork before he got land back. His message to farmers was blunt: do not fall for brokers — whether a company or an agent — and do not sell trees and land for small money. Earlier he had led protests saying he would not allow even one more tree to fall, and that "trees are our parents."
A sapling planted today is not a forest. A forest is soil, water, insects, birds and a hundred years of time.
What the company and government say
Torrent says it obtained forest clearance and all other permissions before work began, that the felling is being done by the Forest Department under those approvals, and that impact will be offset through compensatory afforestation and greenbelt development. Chief Minister Devendra Fadnavis has called the criticism a "fake narrative", arguing that without such storage Maharashtra would need 3,000 MW of thermal power instead.
Now it is in court
The fight has reached the National Green Tribunal's Pune bench. On a petition by activist Adv. Sagar Deore — which alleges that forest land was diverted in violation of the Forest Rights Act and without gram sabha consent — the tribunal has issued notice to the state government. The next hearing is on 17 December.
Why this matters to every family
| The trade-off | For the project | Against the project |
|---|---|---|
| Climate | Stores solar and wind power for night-time use | Old forests store carbon that new saplings take decades to replace |
| Water | Reservoirs hold water for 80 years of operation | Critics say the dams need about 2,300 crore litres of water |
| Safety | Engineered design, statutory approvals | Landslide and earthquake risk in steep Sahyadri slopes |
| People | Jobs and power security | Land, forest rights and gram sabha consent questioned |
What you can do
- Read the project documents before sharing forwards — some posts wrongly blamed a different company
- Ask your local representative how compensatory planting will be verified, tree by tree
- Plant native species (banyan, peepal, jamun, karanj) — not ornamental ones — when your society or school plants trees
- Follow the NGT hearing on 17 December
Development and environment do not have to be enemies. But a 233-hectare forest is not a line item. Maharashtra deserves a transparent public answer on whether a less damaging site was possible.